Week 8

Steel beams are installed.

Temporary walls have been installed inside to hold up the second floor while the new steel beams are installed. There is one long beam installed front to back under the second floor exterior wall. Then they've installed a pair of beams going sideways, under the front-to-back beam. These beams extend further out and land on the new exterior wall below.

The front-to-back beam is being persuaded into place over the side to side beams.

The front-to-back beam is being persuaded into place over the side to side beams.

The steel beam end on a temporary post

The steel beam end on a temporary post

Welding the connections

Welding the connections

The lower beams landing on new interior posts. These are dropped below the ceiling and will get clad with painted wood trim

The lower beams landing on new interior posts. These are dropped below the ceiling and will get clad with painted wood trim

2012-12-19 13.55.25.jpg
Ironically, we've had to remove almost all of the older original house due to deteriorating foundation, dry rot and termites, leaving the 1980's second story addition above.

Ironically, we've had to remove almost all of the older original house due to deteriorating foundation, dry rot and termites, leaving the 1980's second story addition above.

Microwaves are required job site equipment

Microwaves are required job site equipment

Fred Blome

Architect