Week 2

Demolition has been completed and most of the debris has been cleaned out. Typical of older homes is the discovery of hidden damage and "unusual" framing. We found termite and dry-rot damage in several locations. Fortunately most are in areas that are being rebuilt.

2012-11-07 10.18.45.jpg
2012-11-07 10.21.46.jpg
2012-11-07 10.22.21.jpg
2012-11-07 10.20.47.jpg
Termite damage

Termite damage

Dryrot and termites

Dryrot and termites

Recessed floor at old bath

Recessed floor at old bath

This is why there were termites. The old entry was an even older(?) porch with a concrete floor. The dirt underneath was up against the floor framing.

This is why there were termites. The old entry was an even older(?) porch with a concrete floor. The dirt underneath was up against the floor framing.

Those are tree roots from the oak. This pier and one other will be moved to miss the roots.And the job site mascot helps the investigation.

Those are tree roots from the oak. This pier and one other will be moved to miss the roots.

And the job site mascot helps the investigation.

Fred Blome

Architect